Invitation to Bid (ITB)

ESB LaPine Gravel Pit Fence Installation

(Prod)

Manual or Electronic Bids Allowed


ODOT - Agency - Transportation Commission
Issued By
ODOT - Agency - Transportation Commission
ODOT Procurement Office, MS 2-2
3930 Fairview Industrial Dr SE
Salem, Oregon
97302
Contact Terri M Ruddell
Phone 1 (503) 986-2841
Fax  
Email T​e​r​r​i​.​M​.​R​u​d​d​e​l​l​@​o​d​o​t​.​s​t​a​t​e​.​o​r​.​u​s​
Opportunity #
730-33894-19
Addendum # 1
Publish Date & Time
05/17/2019 10:33 AM
Closing Date & Time
Changed
05/29/2019 2:00 PM
Time Zone
Pacific Time
Approx. Time Remaining
All dates are mm/dd/yyyy


Issued For
ODOT - Agency - Transportation Commission
ODOT Procurement Office, MS 2-2
3930 Fairview Industrial Dr SE
Salem, Oregon
97302

Addendum #1 to

Change Bid Submission Deadline from May 28, 2019 @ 2:00 PM to May 29, 2019 @ 2:00 PM.

Add Substantial Completion date (51%) - June 28, 2019

Change Final Completion date from June 28, 2019 to July 30, 2019
Opportunity Comments
ESB ONLY:

This Request for Bids is restricted to qualified contractors who have been certified by the State of Oregon as an "Emerging Small Business" (ESB) per the guidelines of the Certification Office for Business Inclusion and Diversity (COBID). Only Bids from certified ESB firms will be considered for award of this contract. To verify your certification, please contact COBID at (503) 986-0075.

EMERGING SMALL BUSINESS ASSISTANCE PROGRAM: This project is part of the Emerging Small Business (ESB) Assistance Program under Oregon Revised Statute (ORS) 200.160 through ORS 200.200 and as such, Contractor shall comply with all requirements, including the following:

ORS 200.170(3) Eligibility for Assistance. The applicant for assistance under ORS 200.005 and 200.160 to 200.200 must perform at least 51 percent of the labor on any public improvement or maintenance project for which assistance is received using the applicant's own workforce. 1991 c.517 3, 6.
Opportunity Summary
Project Scope: To furnish materials, equipment, labor and performing work to install fencing at the LaPine Gravel
Delivery Requirements
July 30, 2019 
Payment Terms
Net 0
FOB
(Not Applicable) 

Total

Including all charges
US Dollars Only
Manual & Electronic response must express an interest. Manual response must 1st DOWNLOAD the document. Electronic Response [if allowed] – must express interest; select Respond Online & complete response. Instructions can be found in the HELP screens
Control Number: 2059536
Master File: ORPIN-105697-19